Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations Chris Miller on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Multiple start dates in one master project

Status
Not open for further replies.

joostnl

Technical User
Dec 3, 2015
1
NL
Hello users,

I have a question about MS Project.
My company is starting to grow so I have to plan more so I wanna use MS project for this.

I have one master project called: Projects 2016
Next level are individual projects: (That must not be linked to eachother)
Project 1
Project 2
Project 3
Project etc

How can i set a different start dates for each project?
At the moment I can't change this because it's grayed out.
I Saw this movie about a master project and inserting diffrent project files in one. I find this to difficult because I get to much files and if I insert a project I loose my GANT format/color/style etc.
Also i can easily copy the project for a new one because the type of tasks are very simular.


Thanks in advance!

date_change_teopdu.png


start_date_2_veyflh.png
 
The only way you can force tasks to begin on a specific date is with constraints. Create a milestone task "Project Start" - set a must start on constraint and link as usual.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top