Multiple start dates in one master project

Status
Not open for further replies.

joostnl

Technical User
Dec 3, 2015
1
NL
Hello users,

I have a question about MS Project.
My company is starting to grow so I have to plan more so I wanna use MS project for this.

I have one master project called: Projects 2016
Next level are individual projects: (That must not be linked to eachother)
Project 1
Project 2
Project 3
Project etc

How can i set a different start dates for each project?
At the moment I can't change this because it's grayed out.
I Saw this movie about a master project and inserting diffrent project files in one. I find this to difficult because I get to much files and if I insert a project I loose my GANT format/color/style etc.
Also i can easily copy the project for a new one because the type of tasks are very simular.


Thanks in advance!

date_change_teopdu.png


start_date_2_veyflh.png
 
The only way you can force tasks to begin on a specific date is with constraints. Create a milestone task "Project Start" - set a must start on constraint and link as usual.
 