Is it possible to accomplish the following scenario in with Project 2003 ... and if so … any suggestions or advise as to where to start would be awesome!
Say I have a Project that consists of building multiple check-in stations...The entire project deadline is 1 year ... Each check-in station I build should only take 7 to 10 days...I would like to create a "Production Plan" (schedule) for each check-in station I have to build... but keep them all within the same 1 year project. I would need a column to specify the frequency in which each check-in station will take to build (the 7 to 10 days) ... I also need a way to store or retain 1. unique ID for each "Production Plan" 2. # of Tasks per "Production Plan" 3. # of tasks not completed from the previous "Production Plan" 4. Reason the task was not complete 5. # of times a non-completed task was forwarded to the next "Production Plan"
I have created the columns that will hold the data above … but I do not know how to go about putting it all together …
Many thanks in advance ….
gwoman
Say I have a Project that consists of building multiple check-in stations...The entire project deadline is 1 year ... Each check-in station I build should only take 7 to 10 days...I would like to create a "Production Plan" (schedule) for each check-in station I have to build... but keep them all within the same 1 year project. I would need a column to specify the frequency in which each check-in station will take to build (the 7 to 10 days) ... I also need a way to store or retain 1. unique ID for each "Production Plan" 2. # of Tasks per "Production Plan" 3. # of tasks not completed from the previous "Production Plan" 4. Reason the task was not complete 5. # of times a non-completed task was forwarded to the next "Production Plan"
I have created the columns that will hold the data above … but I do not know how to go about putting it all together …
Many thanks in advance ….
gwoman