I've got one task which has two resources, for example:
1 - one man
2 - one machine
Both resources at first were assign with Stand Calendar
8:00-12:00 13:00-17:00
After that I've changed their calendar (resource calendar) to be set with:
The man works 24hrs a day (!! just an experience)
The machine is always available 24hrs per day
The problem I have is that Project doesn't seem to assume the new values (both in graphics and in the sheet where it shows the start and end task).
I'm using P2000.
By the way: in the task calendar I have the "None" option.
Carlos Saraiva
1 - one man
2 - one machine
Both resources at first were assign with Stand Calendar
8:00-12:00 13:00-17:00
After that I've changed their calendar (resource calendar) to be set with:
The man works 24hrs a day (!! just an experience)
The machine is always available 24hrs per day
The problem I have is that Project doesn't seem to assume the new values (both in graphics and in the sheet where it shows the start and end task).
I'm using P2000.
By the way: in the task calendar I have the "None" option.
Carlos Saraiva