Multiple resources to the same task

Status
Not open for further replies.

cmts

IS-IT--Management
Oct 28, 2003
2
PT
I've got one task which has two resources, for example:
1 - one man
2 - one machine
Both resources at first were assign with Stand Calendar
8:00-12:00 13:00-17:00

After that I've changed their calendar (resource calendar) to be set with:
The man works 24hrs a day (!! just an experience)
The machine is always available 24hrs per day

The problem I have is that Project doesn't seem to assume the new values (both in graphics and in the sheet where it shows the start and end task).

I'm using P2000.
By the way: in the task calendar I have the "None" option.

Carlos Saraiva
 
I don't have P2000.

P2002
1. View | Resource Sheet
2. Double-click on the resource
3. In the calendar, select the date(s).
4. Click Nondefault working time.
5. Enter the appropriate From/To working hours.

(People usually come here with real problems not because they were trying an "experience".)
 