I'm a total newbie when it comes to MSProject. I'm just trying to set up a *very* simple task plan for three resources. I'll explain the problem in the simplest test case:
I make two tasks (say "Task A" and "Task B"). For each, I set a duration of 5 days, and for both I set the resource to "John". There's no specific precedence for now, just that both need to be completed. There's *nothing* else set (brand new MSProject 2007 install). The end date isn't important (more a case of, "Here are all the tasks, durations & resources, how long will the project take to complete?").
So the GANT shows both Task A and Task B starting on the same date. Of course, "John" is immediately overallocated, since he can't possibly do two 5-day tasks in the *same* 5-day block of time.
I've played with every combination and permutation of settings in "Level Resources", to no avail. I can't make Project comprehend that one person can't do two tasks simultaneously.
Of course, if I make Task A a precedence of Task B, then they'll line up properly, but I don't really want to have to go through and set "fake" precedents just to avoid overallocation.
What blindly obvious thing am I missing to persuade Project that time is indeed linear and one person can't be in two places at once?
Brad.
I make two tasks (say "Task A" and "Task B"). For each, I set a duration of 5 days, and for both I set the resource to "John". There's no specific precedence for now, just that both need to be completed. There's *nothing* else set (brand new MSProject 2007 install). The end date isn't important (more a case of, "Here are all the tasks, durations & resources, how long will the project take to complete?").
So the GANT shows both Task A and Task B starting on the same date. Of course, "John" is immediately overallocated, since he can't possibly do two 5-day tasks in the *same* 5-day block of time.
I've played with every combination and permutation of settings in "Level Resources", to no avail. I can't make Project comprehend that one person can't do two tasks simultaneously.
Of course, if I make Task A a precedence of Task B, then they'll line up properly, but I don't really want to have to go through and set "fake" precedents just to avoid overallocation.
What blindly obvious thing am I missing to persuade Project that time is indeed linear and one person can't be in two places at once?
Brad.