WaterGypsy
MIS
Hi guys,
we have recently converted from MSP 2003 to 2007 (some users were later moving than others, but the problem is continuing even though everyone is now on 2007).
Since the conversion we have noticed that on occasion MSP will decide to reallocate Actual Work that has previously been entered.
For example: if we had 3, 4, 5, 3 hours allocated for the previous 4 weeks then went in and put in 4 weeks for this week, MSP could change the prior weeks to something like 3.5, 3.8, 5.2, 3.8 (the total always seems to be correct, just the individual figures change).
Does anyone have any idea what might be causing this?
Thanks
Kevin
we have recently converted from MSP 2003 to 2007 (some users were later moving than others, but the problem is continuing even though everyone is now on 2007).
Since the conversion we have noticed that on occasion MSP will decide to reallocate Actual Work that has previously been entered.
For example: if we had 3, 4, 5, 3 hours allocated for the previous 4 weeks then went in and put in 4 weeks for this week, MSP could change the prior weeks to something like 3.5, 3.8, 5.2, 3.8 (the total always seems to be correct, just the individual figures change).
Does anyone have any idea what might be causing this?
Thanks
Kevin