Jackson920
IS-IT--Management
Hi:
I've got a resource loaded schedule in MSP 2007. I have been sending my client the schedule as a PDF, because I don't want them to see assigned resources or work. I just want them to see Task ID, Name, Start, Finish, Predecessor and Successor fields. They are insisting on getting the MPP, so they can do what-if scenarios. My question is how can I freeze the dates in the schedule, so that when I remove work and resources, the dates don't change? Does anyone have any recommendation what the best way to do that is?
Thanks,
David
I've got a resource loaded schedule in MSP 2007. I have been sending my client the schedule as a PDF, because I don't want them to see assigned resources or work. I just want them to see Task ID, Name, Start, Finish, Predecessor and Successor fields. They are insisting on getting the MPP, so they can do what-if scenarios. My question is how can I freeze the dates in the schedule, so that when I remove work and resources, the dates don't change? Does anyone have any recommendation what the best way to do that is?
Thanks,
David