Interesting problem here:
We're just starting a deployment of MS Project Server 2003 and so are beginning our Enterprise Global MPT modifications. When customing an Enterprise Outline Code, one person in our admin group is unable to indent the task when editing the lookup table. He is able to indent tasks when customizing a field in a non-Enterprise file.
Steps to get there:
Options --> Customize --> Enterprise Fields --> Custom Outline Codes.
- Choose a code
- Define Code Mask
- Edit Lookup table (enter in data)
- select one outline code and try to indent (make it Level 2). Nothing happens.
Has this happened to anyone before? Thanks for any help you can provide.
Phyllis
We're just starting a deployment of MS Project Server 2003 and so are beginning our Enterprise Global MPT modifications. When customing an Enterprise Outline Code, one person in our admin group is unable to indent the task when editing the lookup table. He is able to indent tasks when customizing a field in a non-Enterprise file.
Steps to get there:
Options --> Customize --> Enterprise Fields --> Custom Outline Codes.
- Choose a code
- Define Code Mask
- Edit Lookup table (enter in data)
- select one outline code and try to indent (make it Level 2). Nothing happens.
Has this happened to anyone before? Thanks for any help you can provide.
Phyllis