Hi
I am trying to extract data from MS Project file. I am able to extract data from Assignment, Task and Resources table but I need the data in Timephased table. I can extract the data from those 3 table thru OLEDB but I can't get any data from Timephased table. Basically I need to know what are equivalent Timephased table field names in OLEDB. Please help urgently.
Thanks
I am trying to extract data from MS Project file. I am able to extract data from Assignment, Task and Resources table but I need the data in Timephased table. I can extract the data from those 3 table thru OLEDB but I can't get any data from Timephased table. Basically I need to know what are equivalent Timephased table field names in OLEDB. Please help urgently.