Can anyone tell me to show actual time planned on a task as opposed to elapsed time for the task. For example, I want a task to cover 3 weeks but it will only be worked on 5 days during those 3 weeks. So, the schedule should the task taking 3 weeks but the time spent is 5 days. Also, can one set the planned time on a major task but record the actual time against the sub tasks.<br><br>Any help or online references will be appreciated.<br><br>Thank you,<br>Jerry