Hi,
in MS Project 2000, I've added a periodic task,
e.g.
- name: DoHouseWashing
- duration: 1 day
- every week at Monday
- starts March, 18th
- until end of 2002
In the Gantt Chart, I can see the duration column
displayed, and it shows the total duration until
completition (286 days).
Question: I'd like to display only the amount of days,
that I actually plan to work on this task (in my case
42 days). How can I achieve this?
Thanx in advance & best regards,
Volker Kopetzky