I'm trying to create a report on a project plan where I can see a resources name and their tasks for a week I specify.

I've tried to do this by creating a custom report with "Should start finish by" filter but it only shows a list of tasks and their dates but no Resource Names.

Can someone help?!B-(
 
Try exporting the file into EXCEL and use pivot table
 