Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations Chris Miller on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

ms project 2013: Addition of Duration of Activities not correct 1

Status
Not open for further replies.

Nisar Ahmed

Systems Engineer
Sep 20, 2018
1
AE
I am working on MS Project 2013.

Please clink on the link to view screen shot of the activities i had typed with their headings.

My question is "Building Town Planning" in the above image has 3 activities below it. The total duration of all the three activities should be 976 Days. But it is showing total duration as 476 days only. I marked this in the circle. The predecessors are correct.

Some one help to resolve it.

Thanks.


Nisar
nisarahmedpersonal@gmail.com
 
Try adding a calculated field.

Gantt Chart Tools > Format > Columns > Custom Fields ...

Choose from drop down, (upper right) Duration

Pick any Durationn and rename to suite

Add a Formula, choose Field, Duration > Duration

Rollup > Sum

That creates a new custom field. Now you can INSERT a column in your Gantt and select the new duration field you just created.

Does this help?

Skip,
[sub]
[glasses]Just traded in my OLD subtlety...
for a NUance![tongue][/sub]
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top