Nisar Ahmed
Systems Engineer
I am working on MS Project 2013.
Please clink on the link to view screen shot of the activities i had typed with their headings.
My question is "Building Town Planning" in the above image has 3 activities below it. The total duration of all the three activities should be 976 Days. But it is showing total duration as 476 days only. I marked this in the circle. The predecessors are correct.
Some one help to resolve it.
Thanks.
Nisar
nisarahmedpersonal@gmail.com
Please clink on the link to view screen shot of the activities i had typed with their headings.
My question is "Building Town Planning" in the above image has 3 activities below it. The total duration of all the three activities should be 976 Days. But it is showing total duration as 476 days only. I marked this in the circle. The predecessors are correct.
Some one help to resolve it.
Thanks.
Nisar
nisarahmedpersonal@gmail.com