MS Project 2010 - Master project resource alocation

Status
Not open for further replies.

remeng

Technical User
Jul 27, 2006
520
US
I'm trying to use the same resources that are located in a master project for all of the sub projects. I have tried completing the task two different ways. The first is to import / link the sub projects into the master project, then add the resources to the master project. The second way that I attempted to attach them is by adding a project with just resources and link them into the master project. With both attempts, I can see the resources in the master project resource table, but when I use the resource name pull down field in the task, the resources aren't being displayed. What's going on and how can I resolve it?

Thanks,

Mike
 
The resource pool file should be linked to the individual sharer files. Then use the Resource Pool file to create the master project.
 