MS Project 2003 Task Usage View

Status
Not open for further replies.

pmarinelli

IS-IT--Management
Mar 31, 2009
1
US
Hi everyone, I'm new here. Glad to see this resource is available.

I'd like to know if there is a way to turn off the display of resource names in the task name column. I would prefer adding a new column with the resources, to make life easier when exporting to Excel.

Thanks,
Pino
 
The only reason for the Task Usage and the complementary Resource Usage views is to display both the resource and task names in the same column.

In fact, I make considerable use of this when I copy info over to an Excel spreadsheet. Include the column "Assignment" to help you when you are manually reformatting.

If you don't want both the Task Name and the Resource Name in the same column then use View > Gantt.


 