Can you help - I am a new(ish) user to MS Project - I used it in anger about 5 years ago then stopped when I gave up project management work. I have forgotten more than I learned it would appear!
I hid my Start and Finish columns so that I could print a view for a manager that didn't require that information. Super. Now I have gone back to my project and want them back (for a manager that DOES require that info to be printed - and for me as I'm working with it) but I can't find them in the column list!
I have tried Insert column, but the list that comes back does not seem to contain these fields. I have looked in the help for the definitions of all of the fields in the list offered, and none of them is the original Start and Finish columns I hid.
I know the information is still there, obviously, as it's held within each task when I double click it, and is also displayed on the Gantt chart.
Help! What am I doing wrong? All advice appreciated. Many thanks in anticipation.
I hid my Start and Finish columns so that I could print a view for a manager that didn't require that information. Super. Now I have gone back to my project and want them back (for a manager that DOES require that info to be printed - and for me as I'm working with it) but I can't find them in the column list!
I have tried Insert column, but the list that comes back does not seem to contain these fields. I have looked in the help for the definitions of all of the fields in the list offered, and none of them is the original Start and Finish columns I hid.
I know the information is still there, obviously, as it's held within each task when I double click it, and is also displayed on the Gantt chart.
Help! What am I doing wrong? All advice appreciated. Many thanks in anticipation.