Missing Completion Status for root task in MS Project

Status
Not open for further replies.

19862006

Programmer
Jul 26, 2010
1
CA
Hi,
I export my project to XML file, then convert it to MS project. It seems to be that the completion status is missing for the root task(for all other tasks, the completion status which is the check mark seems to be working fine). Does anyone know how to fixed this problem?

p.s. I looked in the XML file, I can see "PercentComplete" is 100 for the root task and all other tasks that is completed.


Thank you,
D
 