jdmwellington
IS-IT--Management
Hi There,
I thought I was a confident MS Project user, however this week I have been puzzled by some of the scheduling behavior I observed when trying to create a schedule in Project 2010 & was hoping someone here could help me out!
I'll keep the example really simple:
*Scheduling mode: automatic, fixed units
*10 tasks
*Each task has a work value of between 1h - 3h
*All tasks can start in parallel, there are no hard dependencies
*I have a single resource
My process:
1) Assign the single resource to each task, however as soon as 8 hours of work had been assigned the over allocation indicators were appearing (understandable)
2) I then entered SS (start-start) dependencies against each task and tried again, the same issue occured
3) I then tried FS (finish-start) dependencies between the tasks which solved the over-allocation but did not give me an optimal schedule e.g. although two FS start tasks had less then 8 hours work, MS project tells me 2 day duration is required to complete them (due to the FS dependency).
I would have expected MS project deal with the fact I have a single resource and tasks with low work values, then help me create the most optimal schedule?
I also tried turning effort drive on/off which made no difference.
Any help with this would be much appreciated!
I thought I was a confident MS Project user, however this week I have been puzzled by some of the scheduling behavior I observed when trying to create a schedule in Project 2010 & was hoping someone here could help me out!
I'll keep the example really simple:
*Scheduling mode: automatic, fixed units
*10 tasks
*Each task has a work value of between 1h - 3h
*All tasks can start in parallel, there are no hard dependencies
*I have a single resource
My process:
1) Assign the single resource to each task, however as soon as 8 hours of work had been assigned the over allocation indicators were appearing (understandable)
2) I then entered SS (start-start) dependencies against each task and tried again, the same issue occured
3) I then tried FS (finish-start) dependencies between the tasks which solved the over-allocation but did not give me an optimal schedule e.g. although two FS start tasks had less then 8 hours work, MS project tells me 2 day duration is required to complete them (due to the FS dependency).
I would have expected MS project deal with the fact I have a single resource and tasks with low work values, then help me create the most optimal schedule?
I also tried turning effort drive on/off which made no difference.
Any help with this would be much appreciated!