ianhawksey
MIS
Hi Guys
I am using 8.3 Framework Mgr, Transformer, Analysis Studio, Report Studio, over Oracle.
I have a database with c10 million rows, essentially date based. I need to fill in the gaps between records, by essentially adding 'dummy' records.
For example, I have records for Week 1 and Week 4. I want to be able to 'add' records for weeks 2 & 3 and calculate/display a cumulative qty from week 1 thru to week 4.
I don't want to do this directly in the database as it adds an overhead of 5 times more records.
My current thinking is to add a calculated measure in Transformer using some kind of MDX functionality.
Is this possible?
Am I thinking along the right lines?
Any suggestions?
Thanks
Ian
I am using 8.3 Framework Mgr, Transformer, Analysis Studio, Report Studio, over Oracle.
I have a database with c10 million rows, essentially date based. I need to fill in the gaps between records, by essentially adding 'dummy' records.
For example, I have records for Week 1 and Week 4. I want to be able to 'add' records for weeks 2 & 3 and calculate/display a cumulative qty from week 1 thru to week 4.
I don't want to do this directly in the database as it adds an overhead of 5 times more records.
My current thinking is to add a calculated measure in Transformer using some kind of MDX functionality.
Is this possible?
Am I thinking along the right lines?
Any suggestions?
Thanks
Ian