Greetings, I am trying to understand material resource usage for reusable material. My made up project is brew 3 batches of beer with 100 reusable beer bottles. Each batch needs 50 so when batch one is done the bottles start being emptied at the rate of 10 per week. Obviously batch two can start at any time.. how do you show the usage of 10 per week and then see the available of 50? It seems easy in my thinking, just cannot figure how to show in MS Project.
Liken this to having 100 tooling machines that are released from assembly line at the rate of 10 per week to be retooled and used on another assembly.
Thanks ... and Cheers