Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations IamaSherpa on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Max hours per year

Status
Not open for further replies.

indianoviola

Technical User
Aug 8, 2010
2
IT
Hi everybody,
I'm currently trying to set a maximum number of hours per year for all the resources in my project (1600 per year). I tried to change the hours per day and the timetable accordingly, but it's not practical nor working properly (depending on the number of working days i'll have more/less than 1600 hours per year).

Any idea on how I could solve this problem?
Thank you,
 
As you've discovered, you probably shouldn't "mess" with hours per day and hours per week.

While I understand what you're trying to achieve, I'm not sure that this is the best way to go about it.

If it were me then I would click on:
View > Resource Usage
Format > Timescale

In the popup
On the Middle Tier tab:
Units: Years
Count: 1
On the Bottom tier tab:
Units: Months
Count: 1
OR
Units: Quarters
Count: 1

Then I would do a copy and paste from MS Project into Excel. You'll actually have to do two of them: one for the information on the left hand side and one for the "grid" information on the right.

In Excel, I'd put in the necessary formulae see what adjustments I needed to make, make them in Project and then loop back to the two copy-and-paste tasks in the previous paragraph.

While you're doing this, remember that *everything* depends on the accuracy of the work and duration estimates. If either of those is inaccurate then the resulting displays will be inaccurate.
 
Thank you PDQBach,
so, If I'm not wrong, there isn't a "magic tool" in Project that let you block the maximum hours per year of a certain resource.
This is what some colleagues kept telling me. Evidently, it was a bluff ;)


Thank you for your suggestion, I'll see what suits best to my project.
 
Not that I know of.

You can change the Max Units but that only comes into play when you are looking at overallocation (it simply sets a number and then checks to see if the resource is below the number or above -- in which case the resource name is displayed in bold red) and when you are doing Resource Levelling -- something which is fraught with peril.

You might be able to do something if you have Project Server (or stand-alone Project 2010) installed ... but I don't and I have very little knowledge in those areas.



 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top