I am using Project 2000. I have created a Master Project File and Resource Pool File. I have created the subprojects in individual files and have made them share the resource pool. I have inserted these subprojects into the Master project. I have leveled without overallocation because I'm using Group resources rather then individual :)

Ok so now our Priority has changed. Project #3 is now #1. I have set project #3's prority to 600 thinking that would make it a higher prority, but nothing changes. What is the correct procedure to make project schedule accordinly when our priority changes?

I would like to be able to change the priority which intern recalculates the order of tasks to be worked.

Please help...thanks.

 
After changing the priority you must again level your resources.
 