Hi guys,
By default, the bars in the Gantt Chart are drawn based on the "Start" and "Finish" values for each task. This gives us a bar length that represents the duration of the task.
By dragging from the left side of the bar to the right, you can also "scroll" the "% complete" for the task.
I´m currently developing a predominantly "Fixed Work" project, using the "Physical % Complete" field to monitor task progress.
I would like to know whether it´s possible to map the bar´s drag behavior to the "Physical % Complete" value as opposed to the "% Complete" Value.
Any help would be greatly appreciated.
Best regards,
-JAC
By default, the bars in the Gantt Chart are drawn based on the "Start" and "Finish" values for each task. This gives us a bar length that represents the duration of the task.
By dragging from the left side of the bar to the right, you can also "scroll" the "% complete" for the task.
I´m currently developing a predominantly "Fixed Work" project, using the "Physical % Complete" field to monitor task progress.
I would like to know whether it´s possible to map the bar´s drag behavior to the "Physical % Complete" value as opposed to the "% Complete" Value.
Any help would be greatly appreciated.
Best regards,
-JAC