Hi,
I am using MS Project 2007 standrard version for planning and tracking the projects.
Currently i am tasked to handle 3 critical projects at the same time. The resources for these projects are more-or-less the same.
Today, i am trying to use the Master Project Plan option, but have a few queries:
1. How can i track the resource load across the projects? Currently the resource usage sheet only shows the resources work for the 1srt project that is embedded in the plan.
2. If there's a slippage in one project, then how can i know whether the other projects are affected?
thanks and regards
Robert
I am using MS Project 2007 standrard version for planning and tracking the projects.
Currently i am tasked to handle 3 critical projects at the same time. The resources for these projects are more-or-less the same.
Today, i am trying to use the Master Project Plan option, but have a few queries:
1. How can i track the resource load across the projects? Currently the resource usage sheet only shows the resources work for the 1srt project that is embedded in the plan.
2. If there's a slippage in one project, then how can i know whether the other projects are affected?
thanks and regards
Robert