Hi all,
I'm new of the forum and I use MS Project Standard 2003 to help my boss schedule tasks in his office. I have a question:
Suppose I create two tasks, say TaskA and TaskB, starting on day 1, and with duration 1 day each.
Now I assign resource A to TaskA and resources A and B to TaskB.
Obviously, resource B can work on TaskB on day 1. On the other hand, resource A is busy on day 1 so he can only work to TaskB on day 2.
Thus, Taks B is stretched on a 2 days duration: resource B does accomplishes 50% of the tasks first, and then resource A finishes the it.
Now, suppose that Task B can be carried on only if both resources work on it simultaneously. This would imply that resource B doesn't start working on TaskB until resource A is available, and on day 2 both resources start working on it togheter.
How do I accomplish this in MS Project?
I'm new of the forum and I use MS Project Standard 2003 to help my boss schedule tasks in his office. I have a question:
Suppose I create two tasks, say TaskA and TaskB, starting on day 1, and with duration 1 day each.
Now I assign resource A to TaskA and resources A and B to TaskB.
Obviously, resource B can work on TaskB on day 1. On the other hand, resource A is busy on day 1 so he can only work to TaskB on day 2.
Thus, Taks B is stretched on a 2 days duration: resource B does accomplishes 50% of the tasks first, and then resource A finishes the it.
Now, suppose that Task B can be carried on only if both resources work on it simultaneously. This would imply that resource B doesn't start working on TaskB until resource A is available, and on day 2 both resources start working on it togheter.
How do I accomplish this in MS Project?