I have encountered a problem with MS Project with a plan that contains many tasks that are less that a day in duration or contain fractions of a day. If a link two such tasks, Project does not seem to start the successor until the beginning of the following day.
Is this a known problem and is there any workaround? I have temporarily used lags/leads to fix it but this is very unwieldy.
MS Project 2003
Is this a known problem and is there any workaround? I have temporarily used lags/leads to fix it but this is very unwieldy.
MS Project 2003