linking tasks in different projects 1

Status
Not open for further replies.

DrJeffB

Instructor
Nov 28, 2011
1
0
0
US
I am linking tasks in different project files. The link shows up in the predecessor file but not in the original successor file. It is listed in the task dialog box predecessor tab but not as a separate maroon line item. Anyone see this before?
 
Hello Dr JeffB,

What are you settings for showing external predecessors and successors?

You don't state what version of Project. For 2007 and earlier -- Tools > Options, View tab - Cross Project Linking options.

For Project 2010 File > Options, Advanced - Cross Project linking options.

I've never seen external predecessors as "maroon line item" so I'm guessing you've done some formatting either to Text Styles for External Tasks or for the Bar Styles.

The setting for Cross Project Linking options are project file by file, so it is entirely possible to see different settings for different files.

I hope this helps.