Hi
I am trying to create a line chart showing Months between Start Date and End Date for a project and using todays date as the data.Therefore showing how far the project has progressed.
Hope someone can help.
Thanks
Get the printed report looking OK, before attemting to insert a chart.
In your selection statement (Report > Selection Formula > Records), you'd probably want to say not isnull(EndDate), to exclude projects that have not yet ended.
I am assuming the two dates are in the same record. If not it is more complex, probably involving grouping for project code.
Madawc Williams (East Anglia, UK). Using Windows XP & Crystal 10