Hi,
I am working with a Gantt Chart in MS Project. In the chart area, there is a task that is suppose to end at some date (6/2008). I would like to draw the "complete through" bar (black bar) to extend past the blue-coloured bar. i.e. move the black bar past 9/2008. Can someone explain how this can be done. Thank you
I am working with a Gantt Chart in MS Project. In the chart area, there is a task that is suppose to end at some date (6/2008). I would like to draw the "complete through" bar (black bar) to extend past the blue-coloured bar. i.e. move the black bar past 9/2008. Can someone explain how this can be done. Thank you