Invalid month in date

Status
Not open for further replies.

simonlly

MIS
Apr 11, 2003
2
HK
I have a Informix online server(VERSION 7) installed under SCO Unix. Recently, I install the IDS 9.4 to a linux server for testing purpose. I used dbexport to export the data from the old server and try to use dbimport in the new server to import the file. However, I obtain the error message "Invalid month in date" when the new server try to import those data with date information.

I think the reason is because the old server storing date in MM/DD/YYYY and the new server storing date in DD/MM/YYYY.

How can I slove the problem?

Thanks in advance.
Simon
 
Simon:

The problem isn't the way the date is stored, it's the way the date is stored or read in externally (such as with a dbimport or load command) which is controlled by the DBDATE shell variable.

It looks like the original dbexport was created with:

DBDATE=MDY4/ # the default

On your new server, DBDATE probably looks like this:

DBDATE=DMY4/

Either unset DBDATE or set it back to DBDATE=MDY4/, perform your dbimport. After the completes, setDBDATE back to the value you desire.

Regards,

Ed
 
Hi Olded,

Thank you very much . After setting the dbdate, I can migrate the data from the old server to the new server now. Thank you very much.

Simon
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top