Interactive - Job stays IDLE after Complete Backup

Status
Not open for further replies.

Skin57th

Technical User
Aug 21, 2001
1
BE
Hi all,

Hope someone can help me out here.
We have 50 site servers with all the same configuration
IBM Netfinity 3000 Archive python 12/24 DAT , BE 6.11
All BE are configured the same.
When I check all the jobs in Execview, some of the jobs are still listed blue

Instead of creating a new shedule for the next day after a successful backup ,there is this job :

Job Name : Interactive
Job Type : None
Job Status : Idle

When we open BE on that server , we receive the msg :
'Tape device is busy or in use by another application'

Veritas says there is still a copy of BE open.
But there is nothing open!
The only solution for this is to stop the BE service en restart it.
But this is for 20-30 servers
And using the AT command to restart the service every night is an option but I don't like it.

Tnx guys
 