Here is my dilemma. Any and all advice would be very gratefully welcome.
Have an existing task (#1) which lasts for 10 days for Resource A who is allocated 100%.
A new task needs to be inserted (#2) which has a 4 hour duration for the same Resource A who needs to allocate the 4 hours (@100%) during the existing timeframe as task #1. Task #2 needs to occur on a specific date.
Any suggestions on how to insert this new task effectively.
My goal is to extend the elapsed duration of task #1 to accomodate the insertion of task #2 and ensure that task #2 takes place on the necessary date which will be driven by a predecessor.
Your help with this would be most appreciated.
Have an existing task (#1) which lasts for 10 days for Resource A who is allocated 100%.
A new task needs to be inserted (#2) which has a 4 hour duration for the same Resource A who needs to allocate the 4 hours (@100%) during the existing timeframe as task #1. Task #2 needs to occur on a specific date.
Any suggestions on how to insert this new task effectively.
My goal is to extend the elapsed duration of task #1 to accomodate the insertion of task #2 and ensure that task #2 takes place on the necessary date which will be driven by a predecessor.
Your help with this would be most appreciated.