Incorrect hours/cost columns

Status
Not open for further replies.

Nina2001

Programmer
Dec 28, 2001
58
US
I have a fairly large project in MS Project 2000. Unfortunately after I put in all my tasks I now have all incorrect totals for the end date, hours, days, and costs columns on the Bolded (Main Task title) rows. See below:

title st date end date cost days hrs

Main Task 7/24/03 12/1/03 $28,042 92.15days 801.2hrs
SubTask 7/24/03 7/25/03 $280 1 day 8 hrs
SubTask 7/25/03 7/28/03 $280 1 day 8 hrs
SubTask 7/28/03 7/29/03 $280 1 day 8 hrs
SubTask 7/29/03 7/30/03 $280 1 day 8 hrs
SubTask 7/30/03 12/1/03 $1,120 4 days 32 hrs

Can anyone answer why it is doing this?
 