I'm trying to import a list of tasks from an Excel 2000 file into Project 2000. I mapped out and imported a start, finish, actual start, and actual finish date. I would like the start and finish dates to dictate the duration of the task but each task that is imported with only a start and finish date (i.e. not yet started) ends up with a duration of 1 day.
I just tried switching my default task type from Fixed Duration to Fixed Units / Effort-Driven. Now the start, finish, and actual start dates are importing correctly but the actual finish date is not importing...
Any advice would be appreciated! Thanks,
Dave.
I just tried switching my default task type from Fixed Duration to Fixed Units / Effort-Driven. Now the start, finish, and actual start dates are importing correctly but the actual finish date is not importing...
Any advice would be appreciated! Thanks,
Dave.