Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations gkittelson on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Import recurring task question

Status
Not open for further replies.

GS2

Programmer
Apr 19, 2001
23
US
I'm new at MS Project and we have 2 different versions, 2002 and 2003; both are Professional editions.

We are attempting to import projects from an Excel spreadsheet on an ongoing basis.

Is it possible to create a recurring task from that import

--OR--

If that's not possible, to import a "one-time" task and then manually change that task to recurring.

Is either senario possible?

Thanks in advance for your help.
 
A recurring task is, actually, just a summary task with a bunch of detail tasks that have two specific factors:

1. Task Priority of 1000 (so it can't be levelled).
2. Task name that is the summary task name and a numeric increment. Once the recurring task is created the algorithm you used is "forgotten" and is not stored anywhere.

I know that doesn't directly answer your question but it may give you the necessary insight to work out a workable solution for your circumstances. If you still need more info, just ask.
 