Hi,
in Project 2010, the task is for 45 days, there is one resource assigned at 100%. The Resource has 10 days holiday at the start of the task.
Project is calculating 36 days as it shows the resource working on the first day of the task even though the resource has a holiday on that day.
Any ideas?
Thanks,
Darryl