The Microsoft web site says there is a switch in the project options to permit editing of the Resume field. I can't find it. I looked through every option and couldn't find it. Can anyone help?
You can add the field to a task view and change the value without having to change any option. The task must have progress (% complete) before the field is calculated. But once calculated you can edit the date by simply typing the new date.
I cannot edit directly in the task view. I assume that you are talking about the table. The resume field (and the Stop field) are locked. Task does show %complete and there is a date in the Resume field. I want to edit that date.
Can you give me the reference to the web page? I am running Project 2010 SP-2 with the April 2014 CU. I can edit the field in both a manually scheduled or autoscheduled task. Ah, wait. Have you disabled splitting tasks? Check File > Options, Schedule and make sure the option "Split in progress tasks" is enabled (checked). It is by default.
This site uses cookies to help personalise content, tailor your experience and to keep you logged in if you register.
By continuing to use this site, you are consenting to our use of cookies.