Hi all,
I am using this formula Switch([Finish]>[Baseline Finish] And [Baseline Finish]<[Status Date] And [% Complete]<100,"Overdue",[% Complete]=100,"Complete",[Total Slack]<0,"Late",[Total Slack]>=0,"On Schedule") in the custom field of the "Text Coulmn", but it isn't working for the Overdue tasks. It doesn't honor the "Status Date", and shows overdue for all the tasks which has paased their baseline date. Does anyone know how to show the status of the project in terms of overdue, Late, Onschedule & Completed tasks using MSP 2010.
Thanks in advance.
I am using this formula Switch([Finish]>[Baseline Finish] And [Baseline Finish]<[Status Date] And [% Complete]<100,"Overdue",[% Complete]=100,"Complete",[Total Slack]<0,"Late",[Total Slack]>=0,"On Schedule") in the custom field of the "Text Coulmn", but it isn't working for the Overdue tasks. It doesn't honor the "Status Date", and shows overdue for all the tasks which has paased their baseline date. Does anyone know how to show the status of the project in terms of overdue, Late, Onschedule & Completed tasks using MSP 2010.
Thanks in advance.