Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations Mike Lewis on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

How to show the overdue, Late, Onschedule & Completed tasks using MSP 2010

Status
Not open for further replies.

AK04

Programmer
Jan 10, 2016
1
AU
Hi all,

I am using this formula Switch([Finish]>[Baseline Finish] And [Baseline Finish]<[Status Date] And [% Complete]<100,"Overdue",[% Complete]=100,"Complete",[Total Slack]<0,"Late",[Total Slack]>=0,"On Schedule") in the custom field of the "Text Coulmn", but it isn't working for the Overdue tasks. It doesn't honor the "Status Date", and shows overdue for all the tasks which has paased their baseline date. Does anyone know how to show the status of the project in terms of overdue, Late, Onschedule & Completed tasks using MSP 2010.

Thanks in advance.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top