How can i not have the link between duration and work on an individual task? Want to have a 4 hour task take place within a given week. Don't care which day it gets done as long as it is completed by the end of the week.
Task name is A
Resource is #1
Work effort is 4 hours
Start date is 1/24
Must finish by Friday 1/28
Don't really care which day it is done on. But do want to show (gantt) the range that it will done within.
Any ideas? I am sure that this is a basic question but haven't had any luck with what I have tried.
Task name is A
Resource is #1
Work effort is 4 hours
Start date is 1/24
Must finish by Friday 1/28
Don't really care which day it is done on. But do want to show (gantt) the range that it will done within.
Any ideas? I am sure that this is a basic question but haven't had any luck with what I have tried.