How to prevent the auto-calculation of the '% Complete' field in MS Project Professional 2013?

Status
Not open for further replies.

VivekG1

Technical User
Feb 6, 2015
2
CN
Hi,

'% Complete' is auto-calculated in MS Project Professional 2013. If I update '% Complete' for a task in SharePoint to 75% and then if I open the task list in MS Project Professional 2013, then the '% Complete' is auto-calculated to 99% which is different than the one in SharePoint ie 75%.

How to prevent the auto-calculation of the '% Complete' field in MS Project Professional 2013?

Please provide solution for this issue ASAP.

Your reply will be greatly appreciated.

Thanks in advance.





 
I'm sorry there is not a method of turning off the calculation for just % complete. You either turn off calculation for the project as a whole or not. Are you working connected to Project Server or merely synching Project and SharePoint outside of server?
 