Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations SkipVought on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

How to prevent the auto-calculation of the '% Complete' field in MS Project Professional 2013?

Status
Not open for further replies.

VivekG1

Technical User
Feb 6, 2015
2
0
0
CN
Hi,

'% Complete' is auto-calculated in MS Project Professional 2013. If I update '% Complete' for a task in SharePoint to 75% and then if I open the task list in MS Project Professional 2013, then the '% Complete' is auto-calculated to 99% which is different than the one in SharePoint ie 75%.

How to prevent the auto-calculation of the '% Complete' field in MS Project Professional 2013?

Please provide solution for this issue ASAP.

Your reply will be greatly appreciated.

Thanks in advance.





 
I'm sorry there is not a method of turning off the calculation for just % complete. You either turn off calculation for the project as a whole or not. Are you working connected to Project Server or merely synching Project and SharePoint outside of server?
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top