Hi,
I'm a fairly new MS Project user and in need of some help tuning the Duration column. I have two staff, A and B; A works 2 hours a day and B works 1 hour a day. I have set the "Hours per day" to 2 hours.
Now this works for A who's hours are the same as Hours per day. However, let say I assign a 4 hour task to B, the "Duration" is shown as 2 days instead of 4. The Gantt chart has B's duration correct though.
Is there a way I can make B also has the correct Duration?
I am able to do this by adding an extra custom column and writing my own formula, but it seems rather surprising to me that Project doesn't handle this by default?
Thanks!
Jack
I'm a fairly new MS Project user and in need of some help tuning the Duration column. I have two staff, A and B; A works 2 hours a day and B works 1 hour a day. I have set the "Hours per day" to 2 hours.
Now this works for A who's hours are the same as Hours per day. However, let say I assign a 4 hour task to B, the "Duration" is shown as 2 days instead of 4. The Gantt chart has B's duration correct though.
Is there a way I can make B also has the correct Duration?
I am able to do this by adding an extra custom column and writing my own formula, but it seems rather surprising to me that Project doesn't handle this by default?
Thanks!
Jack