Hi,
In my project the resources availability is changing from week to week. I have entered this in "Resource Information". For example person A is working 50% of a 40 hour week. BUT when assigning him a 40 hours task the duration of task will still be presented as one weeks, instead of two.
Does anyone have a solution for me
Thanx in advande