Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations Mike Lewis on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

How to link tasks from two different projects in MS Project

Status
Not open for further replies.

onlyonefever

Technical User
Feb 29, 2012
1
US
Hi all-

Did not find in FAQ and keyword search, so I'll throw it out there.

How do I link tasks from one project schedule to a task in another project schedule?

I am using MS Project 2007.

Thanks

Mike
 
The easiest method is to create a consolidated project and then link.

1. Open both projects in Project.
2. Choose Window > New Window.
3. Select both projects in the New Window dialog box.
4. In the consolidated project, select the predecessor task, press and hold the CTRL key and select the successor task.
5. Release the control key and click the Link Tasks button.

No need to save the master file -- but do make sure you save the changed original files.

I hope this helps.

Julie
 