Sorry if this has already been answered - I'm new to this.
If I have a task that takes 5 days of effort, but the programmer can only work 50%, MP changes my 5 days into 10, which is the correct elapsed time (duration). Easy enough I guess at this level, by what about a project with 50 days of effort, and 5 resources who all work different %? It starts to look like a six month project, instead of two months. How can I see that the task is actually 50 days of effort?
%-)
If I have a task that takes 5 days of effort, but the programmer can only work 50%, MP changes my 5 days into 10, which is the correct elapsed time (duration). Easy enough I guess at this level, by what about a project with 50 days of effort, and 5 resources who all work different %? It starts to look like a six month project, instead of two months. How can I see that the task is actually 50 days of effort?
%-)