kpierce123
IS-IT--Management
Hello:
I a trying to figure out a way(best way) to determine a "planned % complete" simply based on the number of days in a task.
For example:
Task Start Date = 3/1/15
Task Finish Date = 3/20/15
So the task is 20 days long
Today is 3/10/15 so "planned % complete" should be 50%
(Today-Start) / (Finish-Start)
=
((3/10/15)-(3/1/15)) / ((3/20/15)-(3/1/15))
=
(10) / (20)
=
50%
Do I just enter this into a custom field as a formula or is there a better way of doing this?
Also, when I tried to do this with a formula, it did not apply to the roll up tasks. So, the bolded tasks were blank.
I am trying to get to a calculated number of the % I should be completed based on the current date and length of the task. I realize this might not be the best way so any
suggestions are greatly appreciated.
I would like to be able to look at my project and see that I am 35% complete, but I should be 50%.
Any guidance is greatly appreciated.
I am using MS Project 2010.
Thanks
kp
I a trying to figure out a way(best way) to determine a "planned % complete" simply based on the number of days in a task.
For example:
Task Start Date = 3/1/15
Task Finish Date = 3/20/15
So the task is 20 days long
Today is 3/10/15 so "planned % complete" should be 50%
(Today-Start) / (Finish-Start)
=
((3/10/15)-(3/1/15)) / ((3/20/15)-(3/1/15))
=
(10) / (20)
=
50%
Do I just enter this into a custom field as a formula or is there a better way of doing this?
Also, when I tried to do this with a formula, it did not apply to the roll up tasks. So, the bolded tasks were blank.
I am trying to get to a calculated number of the % I should be completed based on the current date and length of the task. I realize this might not be the best way so any
suggestions are greatly appreciated.
I would like to be able to look at my project and see that I am 35% complete, but I should be 50%.
Any guidance is greatly appreciated.
I am using MS Project 2010.
Thanks
kp