Jackson920
IS-IT--Management
HI:
I have an MS Project 2013 schedule that doesn't seem to auto-calculate anymore after updates. I have the flag set to autocalculate after updates but it doesn't do it. If I switch an individual task from auto to manual and back again, that task will calculate when I click back to auto, but the task after it which has a FS dependency on it will not change dates as a result. How can I repair this MSP File?
Thanks,
djo
I have an MS Project 2013 schedule that doesn't seem to auto-calculate anymore after updates. I have the flag set to autocalculate after updates but it doesn't do it. If I switch an individual task from auto to manual and back again, that task will calculate when I click back to auto, but the task after it which has a FS dependency on it will not change dates as a result. How can I repair this MSP File?
Thanks,
djo