I've set up a template for projects. Project Managers(PM) will enter in the estimated dates, tell me when they've finished, and I take a snap-shop (Baseline).
My problem is that each PM has several project and will work on each anywhere from 10 to .5 hours a week. MS Project is set up to automatically assume they will work 8hrs a day, 40 days a week. How do I Allocate Time when it's so random? I need an accurate as possible comparison between the baseline time and actual time.
I'd also like to know if there is a way with Project Web, that Actual Hours can be entered instead of choosing percent done.
My problem is that each PM has several project and will work on each anywhere from 10 to .5 hours a week. MS Project is set up to automatically assume they will work 8hrs a day, 40 days a week. How do I Allocate Time when it's so random? I need an accurate as possible comparison between the baseline time and actual time.