How to change baseline project finish date in MSP 2000?

Status
Not open for further replies.

davidd31415

Programmer
Jan 25, 2006
154
US
Does anyone know how to change the baseline project finish date (shown in project statistics) in MSP 2000? I changed the 'baseline start' and 'baseline finish' fields for all tasks in my project but the baseline finish date remains the same.

Thanks,

David
 
Tools | Tracking | Save baseline ...

Answer "yes" to overwrite.
 