Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations Mike Lewis on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

How to calculate ideal work at certain status date

Status
Not open for further replies.

cctanaka

IS-IT--Management
Aug 24, 2005
19
BR
Hello,

I need to compare the amount of finished work ( % finished work) against the the ideal work (work without delays) finished in a status date. How could I obtain the last one?

Thanks in advance.

Carlos Cesar tanaka
Curso de Excel / Access
MPR Informatica
 
Sorry - I don't follow. If you want to compare where the project "should be" consider using earned value analysis. You'll need to have assigned costed work resources, saved a baseline, and have accurate baselines and tracking.
 
Yes I vê done this. It seems correct. I assigned $1 for each resource cost, is that right.

Carlos Cesar tanaka
Curso de Excel / Access
MPR Informatica
 
Yes. Assigning $1 per hour for each resource translates more easily to hours
 
Thanks JulieInMaine.

Carlos Cesar tanaka
Curso de Excel / Access
MPR Informatica
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top