How to calculate ideal work at certain status date

Status
Not open for further replies.

cctanaka

IS-IT--Management
Aug 24, 2005
19
BR
Hello,

I need to compare the amount of finished work ( % finished work) against the the ideal work (work without delays) finished in a status date. How could I obtain the last one?

Thanks in advance.

Carlos Cesar tanaka
Curso de Excel / Access
MPR Informatica
 
Sorry - I don't follow. If you want to compare where the project "should be" consider using earned value analysis. You'll need to have assigned costed work resources, saved a baseline, and have accurate baselines and tracking.
 
Yes I vê done this. It seems correct. I assigned $1 for each resource cost, is that right.

Carlos Cesar tanaka
Curso de Excel / Access
MPR Informatica
 
Yes. Assigning $1 per hour for each resource translates more easily to hours
 
Thanks JulieInMaine.

Carlos Cesar tanaka