I have a task which is fixed duration.
Originally the task is executed by a fulltime employee (20%).
When i replace this resource by a halftime employee i would like MS Project automatic to recalculate the units(40%) because this task should be finished at the same date as with the fulltime resource.
At this moment when i replace the resource, MS Project will complain and changes the duration of my (fixed duration)task. When i replace the resource from fulltime to partime, the task will take longer, when i change from parttime to fulltime the task will finish sooner but the finishdate will stay the same and MS Project will draw a dotted line from the actual finish to the former finish date.
Any suggestions?
Pieter
Originally the task is executed by a fulltime employee (20%).
When i replace this resource by a halftime employee i would like MS Project automatic to recalculate the units(40%) because this task should be finished at the same date as with the fulltime resource.
At this moment when i replace the resource, MS Project will complain and changes the duration of my (fixed duration)task. When i replace the resource from fulltime to partime, the task will take longer, when i change from parttime to fulltime the task will finish sooner but the finishdate will stay the same and MS Project will draw a dotted line from the actual finish to the former finish date.
Any suggestions?
Pieter