how does "start no earlier than" actually work (MS Project)

Status
Not open for further replies.

carpeliam

Programmer
Mar 17, 2000
990
US
I have a "Start no earlier than..." constraint on a particular task. I have not been able to set the task start date to the same date as the constraint date. Why is this? I would understand if the date was before the start date, but on the same day? Liam Morley
lmorley@wpi.edu
"light the deep, and bring silence to the world.
light the world, and bring depth to the silence."
 
Are you doing this through the GUI? When I do this, the start date is automatically set to be the same as the constraint date, I don't need to separately set the start date.
 